Perbandingan (Study Banding) Holding Time (Waktu Perbandingan) dengan Tanpa Holding Time pada Proses Fluxing di PT.Inalum Kuala Tanjung
Abstract
Holding time is the time to produce slag cast with the addition of flux in the oven, the
treatment of the flow in theory, but is always in the field when the temperature is still
high, can not be used. Results of treatment in flow is slag, slag produced
approximately 30 to 40 Kg 200 Kg of metal slag. The calculations used in the
calculation as determined by PT INALUM. On the data obtained in unit 0 to 30
minutes time of the acquisition slag 64%, at the time of 31 to 60 minutes of the unity
of acquisition of the slag of 74.3%, and 61-90 minutes in a slag unit of time of
acquisition of 75.4 per centthen every 1 ton of aluminum bars is a unit of acquisition
of slag of ± 75%, so if the slag below 50%, then the metal must be recycling.
Collections
- Diploma Papers [1126]