Analisa Konsep Cadangan Waktu dengan Penjadwalan Proyek menggunakan Metode Precedence Diagram Method (Pdm) (Studi Kasus : Proyek Pembangunan Jembatan Sei Belawan)

Date
2023Author
Hutasoit, Rintar Marselino
Advisor(s)
Hasibuan, Gina Cynthia Raphita
Metadata
Show full item recordAbstract
On the Sei Belawan Bridge project several times experienced delays in work, so
that activities on the project were ineffective which could result in project delays.
Schedule preparation using the Precedence Diagram Method (PDM) can find out
the relationship between one activity and another activity specifically. This
research aims to make the project have time reserves as a safety factor so that the
project does not experience delays.
The results showed that the value of time reserves in the initial situation of the
project was positive (+) 36 days, while the value of time reserves in the 26th week
of work implementation was positive (+) 8 days and the value of time reserves in
the 35th week of work implementation was positive (+) 2 days. Analysis of the
erosion rate of time reserves until week 35 reached 94.44%, and the rate of
completion of activities has reached 96.83%, then the remaining work is 3.17%,
while the remaining CW is 5.56%. Thus, there is still a positive remaining (+) 2
days of additional time for further work