Evaluasi Penjadwalan Proyek dengan Metode Line of Balance (LOB) (Studi Kasus : Proyek Pembangunan Jalur Kereta Api Medan - Binjai Km 2+300 s/d Km 2+850, Sumatera Utara)
Evaluation of Project Scheduling Using The Line of Balance (LOB) Method (Case Study: Medan - Binjai Railway Construction Project Km 2+300 to Km 2+850, North Sumatra)
Abstract
A project requires a good project scheduling method so that implementation
can run smoothly and avoid losses in terms of time or costs. This research uses the
Line of Balance scheduling method. The aim of this research is to analyze the
comparison of work implementation periods between scheduling using the Line of
Balance method and existing methods. The research was carried out on the Medan
- Binjai Cross Railway Package 3 construction project. The research used a
comparative study type of research with a qualitative research method approach.
This research uses secondary data obtained from the project in the form of
Barcharts and S-Curves. Scheduling duration will be applied to pier work. Based
on the time schedule, activities are grouped into 26 component types of activities.
In this research, several jobs will be combined to produce 9 activity components
with appropriate durations and a dependency logic between activity components
will be arranged. The series of activities in this method must not intersect with each
other. From the calculation results of scheduling using the Line of Balance method
and the existing duration obtained is the same as the initial duration, namely 112
weeks. In order to obtain a faster scheduling duration than the initial scheduling,
it is necessary to accelerate several work items by changing the finish to start
relationship to start to start. The results of the analysis show that the duration
required for project completion is 110 weeks. Meanwhile, the duration of work in
the existing scheduling is 112 weeks, so there is a reduction in the total duration of
2 weeks when implementing the Line of Balance scheduling system. The Line of
Balance method has the advantage of determining the exact start time of work, and
can identify conflicts between jobs.